Ski–Askim–Mysen–Rakkestad–Sarpsborg
From the inland railway to the digital railway
The inland route was once the main-line proposal
In 1866, Landmark proposed an inland main line towards Sweden, with branches serving coastal towns. Østre linje therefore emerged from a dispute over which communities should receive the railway, rather than simply as an extra local branch. 08
Parliament’s 1874 settlement took the route through Mysen, farther east than an earlier riverbank alignment. A possible future connection north towards Øyeren or Kongsvingerbanen helped justify the choice. That link remained a proposal. 08
Askim opened before the through connection
Regular trains from Kristiania reached Askim on 21 July 1882. Construction continued farther south until through services between Ski and Sarpsborg began on 24 November. 08 09
The eastern branch joined the two arms of Østfoldbanen at Ski and Sarpsborg. Today the Norwegian Railway Directorate gives its length as 78.96 kilometres, through Askim, Mysen and Rakkestad. The two branches reunite at Sarpsborg. 01
The railway carried the produce of the interior
Farms sent grain, milk, potatoes, meat and timber to markets by train. Fertiliser and fuel travelled back into the district. Goods traffic made the station a link to distant customers as well as a place for passenger journeys. 08
A chain of station settlements took shape
Tomter, Spydeberg, Askim, Slitu, Mysen, Eidsberg and Rakkestad received stations when the line opened in 1882. Later additions included Heia in 1896 and Knapstad in 1912. The railway brought a new hierarchy of stopping places to an older landscape of farms and roads. 02
The stations drew commerce and settlement towards the railway. Their importance therefore extended beyond the number of trains: an inland place could become a local centre because goods, workers and customers could reach it throughout the year. 02 10
Askim combined a railway with power and manufacturing
Askim’s industrial growth brought the railway and Glomma’s electricity together. Per Mathias Røwde chose the town for Viking’s rubber factory because it offered power, a railway connection and favourable local taxation. The factory was ready for use on 17 January 1920. Rubber footwear was followed by other products, including tyres, and the works became a major local employer. 10
This explains why the station belongs in the industrial history of the town. The railway offered a route for materials, finished products and people, while electricity supported production. Their combined presence helped make a factory settlement into a substantial industrial town. 10
Power-station branches connected the railway to Glomma
Kykkelsrud’s first generating units entered service in 1903, following construction from 1900. Glomma’s waterpower became a major industrial resource after the main line had opened. Further development and joint schemes followed during the twentieth century. 11
Vamma’s history began with Sam Eyde’s plans for a fertiliser works. Those plans were abandoned, Hafslund took over, and the first generating units entered service in 1915. 12
The railway branch towards Vamma had been built in 1908–1910 for construction traffic. Private railways carried materials from Askim towards riverside works, extending the transport network beyond the main-line station. 03
Solbergfoss gained a railway of its own
The branch from Askim towards Solbergfoss was built in 1915–1917 to carry goods for the power-station works. The first generating station opened in 1924, with a building designed by Bredo Greve. This private line linked the main railway to a major construction site and then acquired a longer life serving local passengers. 03 13
The branch finally closed in 1965, and the rails were removed in 1970. It remains distinct from Østfoldbanen itself: a local industrial railway whose traffic grew from the river’s development, rather than another part of the state railway’s route to Sweden. 03
Motorcars brought trains closer to the villages
Motorcar operation began on Østre linje in 1928. Railway historians Langård and Ruud describe 38 new stopping places established that year, initially often at road crossings rather than purpose-built stations. More formal halts followed from 1932. The lighter trains extended the railway’s everyday reach into places that had previously lain between its principal stations. 14
The fortifications beside the Langnes railway bridges
At Langnes the railway crosses Glomma and its side channel beside older Norwegian defences. Jernbaneverket’s heritage survey identifies a battery from 1899 and a bridge gallery built in 1913–1917, intended for the close defence of the railway bridges. The rock-cut passages and protected firing positions were therefore in place before the German occupation. Their purpose was to defend the crossing against an attack from the east. 04 15
The works formed part of a wider defensive system. Parliament decided in 1913 to build galleries at Langnes railway bridge and Fossum road bridge. They were handed over with Høytorp and Trøgstad forts in 1918. 15
The gallery at Langnes lies on the Spydeberg side of Glomma, with additional protection on the island between the railway bridges. The surviving corridor and side rooms belong to the bridge-defence complex. The present railway superstructures are later: the 2004 railway heritage survey dates the main-channel bridge to 1947 and the side-channel bridge to 1951, retaining older masonry supports. The view therefore brings several generations of railway and military construction together. 04 16

CC BY-SA 4.0 · Resized and converted to WebP; cropped in the page layout
The Glomma crossing became a wartime break in the line
The original NSB Oslo-district wartime report records a complete interruption of Østre linje after the bridges at Langnes over Glomma and near Rakkestad were blown. A railway built to join the inland district to the wider network could become isolated when a few strategic crossings were lost. 17
At Høytorp fort near Mysen, Norwegian forces fought on 13–14 April 1940 before surrendering. German troops used it as a garrison and convalescent camp, adding an occupation layer to a district already shaped by Norwegian border defences. 15
Mysen and Momarken: prisoners, liberation and the station
The occupation also left a camp history close to the eastern line. At Momarken outside Mysen, prisoners brought from Grini began constructing SS-Lager Mysen in March 1945 under Hans Aumeier. It was planned as a concentration camp but was never completed. The distinction between the intended camp and what actually existed in the last weeks of the war is essential. 18
An archival photograph shows Norwegian prisoners leaving through Mysen station on 8 May 1945. In the weeks that followed, former Soviet prisoners of war arrived in Mysen and were accommodated at Momarken; later the camp housed displaced Polish people who had been subjected to forced labour. The railway remained part of this history after liberation, bringing people to temporary shelter and helping others leave captivity behind. 19
Electric traction arrived in 1958
Østre linje was electrified in 1958, well after electric trains had reached the western route. The change belongs to the postwar modernisation of the railway, yet it did not bring centralised traffic control to the branch. Electric trains continued to run within a railway organised around locally staffed stations. 01 07 06
Station staff and train messages organised the traffic
Before ERTMS, Østre linje was locally staffed and lacked remote traffic control. Station dispatchers, known as togekspeditører, exchanged manual train messages—togmeldinger—using signal telegraph and, in later years, train radio. Signal telegraph was still part of the line’s equipment in 1999; train messages remained central to its locally managed traffic. 05 07
The arrangement depended on people working at individual stations. In 2003, Transport Minister Torild Skogsholm described an old infrastructure with few crossing opportunities and limited capacity. A delay inherited from the busy Oslo–Ski approach could become harder to recover farther down the branch. Additional rush-hour staffing at Kråkstad was intended to make crossings more flexible. 20
A through railway acquired a quieter southern section
Regular traffic south of Rakkestad diminished in the early 2000s, while the physical railway remained available. In 2013, Transport Minister Marit Arnstad confirmed that Rakkestad–Sarpsborg had no scheduled trains but was open to traffic. Reintroducing a passenger service required more than leaving the rails in place: station facilities, crossings and the approach to Sarpsborg also needed attention. 21
The distinction matters when reading proposals for reopening. A line can survive as infrastructure while lacking a regular service. An improved signalling system can also coexist with limits elsewhere in the route and at its junction stations. 21 22
From a test section to Norway’s first ERTMS railway
Jernbaneverket officially inaugurated an ERTMS test section on 11 December 2013. Further trials and preparation followed before the full eastern branch entered normal operation with the new system on 31 August 2015. 23 01
The change moved signalling information into the driver’s cab and introduced remote control to a route that had never previously had it. Østre linje became Norway’s experience route for the European system. Its significance lay in the combination of new equipment, changed working methods and practical experience for a national programme. 07 06
The change altered railway jobs as well as equipment
Former dispatcher Jorund Gretland later recalled having worked at every station between Ski and Mysen. ERTMS in 2015 removed those local dispatching posts, while maintenance and traffic-control staff needed different skills. The history of the conversion is therefore also a history of work: knowledge of relays, lamps and local station routines had to meet a more computer-based railway. 06
The first months were difficult. In a 2017 public account, Bane NOR’s Sverre Kjenne acknowledged problems from September 2015 to April 2016 and reported better operation from June 2016. The pilot’s later reputation should be read alongside that early period of adjustment. 24
The connection at Ski remained a separate political question
Parliament’s 2013 transport debate already linked Østre linje’s future to Follobanen. One majority wanted eastern-line trains to use the new route and accepted that growing traffic could later require a different connection at Ski. Another majority criticised the handling of the connection and sought more crossing loops on the branch. Signalling renewal and the capacity of the wider network were separate investments. 25
In October 2025, Transport Minister Jon-Ivar Nygård referred to a 2022 assessment which found insufficient traffic to justify extending the passenger service from Rakkestad to Sarpsborg or Fredrikstad, at least before the Moss double-track works and a new eastern-line connection south of Ski were finished. The government prioritised improvements on Vestre linje; regular freight on the eastern branch would require further investment. 22
By October 2026, Bane NOR had sent the new Ski–Kråkstad scheme for final ministry consideration. The proposed 5.2 kilometres of double track and a new connection would allow eastern-line trains to reach Follobanen without crossing other train paths within Ski station. Bane NOR expected a planning decision in the first quarter of 2028, followed by the budget and investment decisions needed for construction. 26
The old railway remains visible in preservation work
Mysen’s former locomotive shed now provides a home for railway preservation. Norsk Jernbaneklubb’s freight-wagon group describes work there on historic wagons, snow-clearing equipment and Padda, a railcar from Solbergfossbanen. The collection brings several parts of the district’s railway history together: the state line, its industrial branches and the rolling stock that served them. 27
A railway in dates
The railway through time
An inland main-line proposal
Landmark proposed an inland main line with coastal branches. 08
Two routes through Østfold
Parliament chose a coastal and an inland route as parts of Smaalensbanen. 02
The main alignment settled
Parliament fixed the two-route scheme through Ski and Sarpsborg. 08
Regular trains reach Askim
Askim joined the regular timetable from Kristiania. 08
The complete eastern line opens
Through operation began between Ski and Sarpsborg. 09
Kykkelsrud begins generating
The first generating units entered service after work began in 1900. 11
The Vamma branch is built
A private railway carried goods for the power-station works. 03
Bridge galleries authorised
Parliament approves galleries at Fossum road bridge and Langnes railway bridge. 15
Vamma begins generating
The first two units entered service under Hafslund after the fertiliser-factory proposal had been abandoned. 12
A railway to Solbergfoss
The private branch was built from Askim for the hydroelectric works. 03
Fortifications formally delivered
Høytorp, Trøgstad and the bridge galleries are handed over together. 15
Viking’s factory is ready
The rubber works brought a new industrial scale to Askim. 10
Solbergfoss opens
The first large power station was completed. 13
Motorcar services and new stops
Motorcars brought 38 new stopping places to Østre linje, many initially at road crossings. 14
Bridges interrupt the line
The NSB wartime report records the eastern route closed after bridge demolitions at Langnes and Rakkestad. 17
Mysen camp construction
Prisoners from Grini begin work at Momarken; the camp is never completed. 18
Prisoners leave through Mysen
An archival photograph records the departure of Norwegian prisoners through the railway station. 19
Langnes bridge renewal
The present main-channel and side-channel bridge superstructures date from 1947 and 1951 in the railway heritage survey. 04
Electric operation
The eastern line gained electric operation. 01
Solbergfossbanen closes
The private branch’s passenger life ended; its rails were removed in 1970. 03
Capacity depends on station staffing
The transport minister described the branch as not remotely controlled; extra rush-hour staffing at Kråkstad was planned. 20
The ERTMS test section is inaugurated
Jernbaneverket marked the beginning of its practical test route. 23
A difficult starting period
Bane NOR later acknowledged startup problems before improved operation from June 2016. 24
Norway’s first ERTMS line enters normal operation
The Ski–Sarpsborg route changed to the new system. 01
A southern extension remains uncommitted
The transport minister explained why the government was prioritising the western line rather than a regular passenger extension beyond Rakkestad. 22
The new Ski connection awaits a planning decision
Bane NOR expected final planning approval in the first quarter of 2028, before budget and investment decisions. 26
Sources
Read further
Open each original source, or use Google Translate to read Norwegian pages in English.