Oslo S–Ski
Planning, construction and the years after opening
The railway problem came first
Follobanen began as a capacity project for the crowded railway south of Oslo. The National Transport Plan for 2010–2019 described the existing Oslo–Ski route as exceeding its peak-hour capacity and argued for a new double track. The project also offered a way to use the older Østfoldbanen more effectively. Its eventual construction method grew out of that railway problem: the original planning standard was 200 km/h, while the advantages and costs of designing for 250 km/h were still being examined. 04
How the tunnel concept developed
In her published account, Bane NOR TBM project manager Anne Kathrine Kalager traced the comparison back to a six-person study group formed in 2007, combining conventional tunnelling and hard-rock TBM experience. Its 2008 conclusions distinguished a single large double-track tunnel from two smaller single-track tubes: the latter made a central TBM approach more attractive. Jernbaneverket selected twin tubes in June 2010, then developed both excavation alternatives before choosing four machines from Åsland in 2012. 05
The early budgets and the political coalition
The preliminary 2013 estimate was NOK 20 billion, in 2013 prices. 06
The 2014 parliamentary documents distinguish NOK 1.22 billion set aside for that year’s work from the framework for the entire project. After external quality assurance, the recommended management target was NOK 24.4 billion and the cost ceiling NOK 26.3 billion, both in 2014 prices. Support crossed the government–opposition divide. Labour, Christian Democrat, Centre and Liberal committee members also pressed for a capable connection from the eastern Østfold line and protection of a possible future high-speed branch. 07
Why four tunnel boring machines?
Jernbaneverket chose mechanised excavation for the main tunnel in late 2012. In its contemporary explanation, access to one large construction site and environmental considerations were central to the decision. 08
Project adviser Multiconsult identified the long tunnel, industrial production, a well-placed large site and the ability to limit access headings as advantages. Four double-shield machines could excavate the two parallel tubes from the middle: two towards Oslo and two towards Ski. Ghella gives the bored section as 18.5 kilometres per tube, with an internal diameter of 8.75 metres. 09 10
Åsland became the construction hub
Before the machines could start, Åsland needed access tunnels and underground assembly halls. The transport minister fired the ceremonial first blast there on 20 June 2014, during preparatory works. AF Gruppen dates its contract for logistics tunnels and assembly caverns for Acciona Ghella to June 2015. Conventional excavation therefore enabled the mechanised drives. 11 12
The surface site also contained the factory making concrete lining segments. As the machines advanced, they left lined bores behind them. Multiconsult described most of the crushed rock as intended for reshaping terrain at nearby Gjersrud–Stensrud, with some material taken to external deposits. Åsland was both a production centre and the meeting point between the underground railway and a much larger surface landscape project. 09
From launch to four breakthroughs
The official start of tunnel boring was 5 September 2016. On 11 September 2018, the two northbound machines, Dronning Eufemia and Dronning Ellisiv, broke through into previously excavated caverns beneath Ekeberg. Each had completed roughly nine kilometres from Åsland. 13 09
The southbound pair completed their drives near Ski on 26 February 2019. Bane NOR marked the completion of roughly 36 kilometres of bored tunnel across both tubes, alongside sections excavated by blasting and rock splitting. Excavation was followed by the installation of track and the railway’s technical systems. 14
Blixtunnelen: Norway’s longest railway tunnel
Blixtunnelen is Norway’s longest railway tunnel, with two separate single-track bores. It is named after Peter Andreas Blix, the architect associated with Østfoldbanen’s original station buildings. 01 15
The tunnel contract extended beyond excavation. Ghella lists the railway technical systems in its scope, with signalling excluded. AF Gruppen's work also reached the conventionally excavated northern section beneath Ekeberg, where remaining civil and concrete works were completed after the original contractor's departure. This was an interface between several construction methods and contracts. 10 12
A later milestone came in March 2022. Acciona reported that the tunnel electricity distribution system was energised from 23 March and the work completed within a week. The announcement explicitly said the tunnel work was still unfinished: energisation enabled further preparation for service rather than marking the opening. 16
A railway through medieval Oslo
At the Oslo end, construction crossed the medieval town. NIKU records archaeological excavations along the railway culvert from 2013 to 2025, the largest in medieval Oslo for more than a century. Buildings, streets, wells, water pipes and thousands of objects emerged from the works. 17
The city impact was planned as more than a covered railway. Oslo municipality's 2018 project document traces an agreement with Jernbaneverket and Riksantikvaren to summer 2012: put the railway in a covered culvert, then restore terrain and make a larger park above it. Archaeology, railway construction and public space became linked parts of the same project. 18
Condotte's financial crisis stopped two packages
Condotte held two contracts worth approximately NOK 3.2 billion together. Bane NOR’s 2017 accounts record liquidity problems beginning that summer and worsening in November and December. Condotte petitioned the Rome courts for bankruptcy protection on 8 January 2018. Its Follobanen subcontractor debt was then approximately NOK 235 million. Unpaid subcontractors left the site. Bane NOR terminated the contracts, took over project management and paid the outstanding debt to restart work, acquiring a claim against Condotte. The company’s packages covered the Oslo approaches and conventionally excavated tunnels; AGJV held the separate main TBM contract. 19
The Italian legal record adds precision to the word “bankruptcy”. Condotte entered extraordinary administration on 6 August 2018. A January 2026 ministerial decree still concerned the liquidation phase of that procedure, following cessation of business ordered in July 2024. The January 2018 protection petition, extraordinary administration and later liquidation are distinct steps. 20
Skanska's procurement case
The Skanska case concerned how a contract was awarded, rather than Condotte's later insolvency. In its unanimous judgment of 17 December 2018, Borgarting Court of Appeal found that Condotte's offer for the Ekebergåsen–Oslo S works should have been rejected because its rock-reinforcement solution departed from minimum tender requirements. The court held that Skanska would probably have won the contract. It awarded NOK 272.8 million in damages and NOK 2,632,497 in appeal costs. Leave to appeal to the Supreme Court was refused. The judgment is LB-2017-94201; its procedural record identifies HR-2019-763-U. 21
The later government-commissioned evaluation records NOK 345 million including interest paid in May 2019. That payment total must not be confused with the NOK 272.8 million principal awarded on appeal. 22 21
The one-year delay becomes public
On 24 January 2019, Bane NOR announced that December 2021 was no longer a realistic opening date. It recommended December 2022 instead. The company attributed NOK 1.6 billion in additional costs to the Condotte problems and also identified unexpectedly difficult ground conditions. It sought a cost-ceiling increase from NOK 28.5 billion to NOK 30.7 billion in 2019 prices. Those figures describe a recommendation announced at that moment: the older NOK 26.3 billion framework had been price-adjusted, and Parliament still had to consider the revised ceiling. 02
Further increases, and a political argument
Parliament authorised a NOK 30.907 billion ceiling on 11 December 2019. The 2020 railway white paper, using 2020 prices, linked the increase to the terminated Condotte contracts and worse ground conditions. It also identified an estimated NOK 1.1 billion currency loss over 2017–2020 against the euro exchange rate underlying the project. Another increase of up to NOK 5 billion was then considered necessary. On 18 December 2020, Parliament authorised NOK 36.570 billion for the project in the 2021 budget. A project ceiling authorises commitments over several years; it is not the sum spent in that single year. 23 24 25
The argument was also about what rising costs displaced elsewhere. In the 2020 committee report, Labour and Socialist Left members wanted a broad evaluation and questioned whether a consultancy review would be sufficient. They warned that overruns on projects already near completion constrained Parliament’s choices and threatened funding for other railway schemes. 26
More than one explanation for the overrun
The independent Oslo Economics evaluation published in 2020 compared costs on a common 2020-price basis. Against the 2014 quality-assured estimate, it identified NOK 5.2 billion of growth plus NOK 2.9 billion associated with major premise changes and events, producing an expected NOK 35 billion cost. It highlighted complexity and delay, difficult ground and insufficient early detail design, especially around the Oslo S approaches. The documented management systems appeared broadly sound, but the evaluation could not verify day-to-day management within its remit. It also found the early estimate too optimistic. 22
Settlements and the decisions before opening
AGJV's disputes did not form one continuous case. PwC's June 2023 evaluation records a NOK 555 million settlement dated 3 May 2019 and a second settlement on 15 January 2021, involving EUR 43 million. These were negotiated agreements, not court awards. 27
The government’s 2023 external review traced another consequential decision: copper replacement of aluminium conductors was ordered in April 2022, then waived in the handover agreement because Bane NOR considered it incompatible with the planned December opening. The review connected the later May 2023 line failures with alkaline drips onto the retained aluminium conductors. 28
Eight days of service, then a long closure
Passenger service began on 11 December 2022; the royal opening ceremony followed on 12 December. Heat and fire in power-cable joints and end terminations near Ski stopped traffic on 19 December. A second fire occurred during testing on 23 December. These are separate dated incidents, rather than one fire spanning several days. 28
The first eight days of passenger service were followed by a closure lasting until 5 March 2023. The promised faster journey to Oslo was replaced by a prolonged period of repairs and changing forecasts. 29
Why the December electrical system failed
Bane NOR's internal investigation identified a combination of water dripping onto an insulator and deficiencies in cable joints and end terminations. Its explanation was that water probably passed a joint between concrete lining segments and became alkaline after contact with grouting material. Deposits left as droplets dried allowed electrical flashover; repeated faults placed demands on the cable system which defective connections could not withstand. 30
The investigation concluded that properly executed cable joints and terminations should have withstood the fault currents. It connected leakage and repeated electrical faults with defects in the connections, explaining how several failures combined to stop the railway. 30
Repairs, postponed promises and the March return
The first repair period brought further setbacks. Bane NOR records new heating and smoke in the Ski switching building on 11 January 2023, in the part serving traffic south of Ski. Its January account describes inspection and repair of connections, repeated changes to the reopening forecast and, on 25 January, postponement without a new date. 31
Test running resumed on 5 February. The final programme continued while measurements and repairs were assessed. Ordinary passenger traffic returned on 5 March 2023, restoring the timetable that had been intended from the previous December. 32 29
May 2023: a different electrical failure
Leakage remained significant after the March reopening. Bane NOR's situation report dates a line failure to 22 May 2023: alkaline drips from the roof caused a power cable to break and contact a train, which stopped in the tunnel. On 25 May, both tubes were closed for checks following that incident. 33
By December, Bane NOR had announced replacement of the aluminium overhead conductors with copper and simplification of the electricity supply. Alkaline water attacking aluminium was the reason given for the May break. Water sealing and the choice of electrical materials had become continuing concerns after the railway reopened. 34
Winter brought ice into the failure story
Bane NOR’s 2023 annual report records ice formation beside the overhead contact system on 6 December 2023. Its electrical annual report describes icicles reaching conductors in the tunnel crown and causing short circuits, with the southern section near Ski identified as the most severe cold zone. 35 36
In March 2024, Bane NOR linked improved sealing to less dripping and less winter ice. The winter problem added another reason to address water entering the tunnel, alongside its effects on electrical equipment in warmer weather. 37
The 2024 rebuilding campaign
From 15 April 2024, one tube at a time was taken out of normal service. The campaign replaced aluminium conductors with copper, sealed leakage points and adjusted track gauge to reduce vibration. Jernbanedirektoratet explained that the installed track had narrowed by a few millimetres and could be adjusted despite being slab track. Most peak-direction trains used the available tube while other services used the older route. 38 39
Nettpartner dates completion and reopening of both tubes to 15 December 2024. Its account records replacement of the aluminium conductors throughout the tunnel and associated work in the frost zones. Jernbanedirektoratet's 2025 annual report, published in 2026, subsequently described high operating reliability after the upgrade and reported 91.7 percent punctuality on Follobanen in 2025. 40 41
The 2023 reviews challenged procurement and quality control
PwC’s evaluation for Bane NOR’s board identified weak follow-up of contractors among the causes of the failed start. Its public summary called for progress and quality to receive more weight in future large contracts, recording that price had carried an 80 percent weighting on Follobanen. The findings connected the physical railway with the commercial and organisational choices used to deliver it. 42
Accountability continued after reopening
Reopening did not end scrutiny of management. In its follow-up published on 27 November 2024, Riksrevisjonen found implementation of earlier recommendations unsatisfactory. It reported that measures after the Follobanen evaluations to improve risk management and internal control had not yet been implemented, and that cost control in several major railway projects remained weak. It also recognised improvements in the ministry’s oversight. 03
Separate criminal cases over work charged to the project
Transparency International Norge’s 2026 court compilation records two January 2026 convictions linked to a Follobanen project. A Bane NOR project manager and a contractor’s operations manager received prison sentences of one year four months and one year ten months for aggravated corruption and financial breach of trust. Workers and materials charged to the railway had been used on private properties. The compilation identifies both judgments as final. 43
The tunnel contract reaches judgment in 2026
Oslo District Court delivered judgment on 17 June 2026 in the final-account and warranty dispute over AGJV’s tunnel contract, case 23-053675TVI-TOSL/01. According to CMS Kluge, which represented Bane NOR, the court ordered AGJV to pay a net NOK 181.6 million after set-off, plus interest, and NOK 33.7 million in legal costs. Additional-payment claims, delay penalties and warranty claims for water-leak repairs formed part of the dispute. AGJV succeeded on some claims, while the resulting balance favoured Bane NOR. 44
On 4 September 2026, NTB reported Bane NOR procurement director Martin Rosenlund’s confirmation to Bygg.no that AGJV had appealed and that Bane NOR was preparing its response. The first-instance judgment had therefore been taken into a further stage of litigation. 45
Åsland's environmental legacy continued
The surface legacy continued after the trains started. NIBIO's report on 2024 water monitoring found that ecological effects from Åsland runoff remained similar to 2023, with sulphate and uranium the main concerns. It recorded no observed acute toxic effects on bottom fauna while retaining uncertainty about chronic exposure and combined effects from other urban and industrial pressures. 46
On 7 April 2026, Statsforvalteren announced a permit for restoration work and moving material at Åsland. Conditions included limits on substances in discharged water, including sulphate, and continued monitoring after the construction work. The history thus extends beyond excavation and opening: restoring the construction landscape and following its water effects remained live obligations in 2026. 47
A ceiling is still not a final bill
The government’s October 2026 transport budget proposal for 2027 still listed Follobanen’s current cost ceiling as NOK 37.535 billion. Its comparison table is headed in 2027 kroner, but a footnote says the original NOK 28.626 billion comparator was indexed only through 2021 because spending had exceeded the original ceiling. The proposal also anticipated about NOK 0.5 billion for closing works in 2027. These figures describe budget limits and proposed future expenditure; the project’s final audited account is a separate matter. 48
The network around Ski continued to develop
The new railway also changed the importance of its connections. By October 2026, Bane NOR’s proposed 5.2-kilometre Ski–Kråkstad scheme was awaiting ministry consideration. It would give Østre linje a new connection towards Follobanen, with a planning decision expected in the first quarter of 2028 followed by investment and funding decisions. 49
A railway in dates
The railway through time
The excavation study begins
A six-person group compared conventional excavation with hard-rock tunnel boring. 05
Capacity shapes the transport plan
The national plan prioritised a new Oslo–Ski double track. 04
Two single-track tubes selected
Jernbaneverket selected a twin-bore tunnel concept. 05
The main tunnel method is chosen
Mechanised excavation was selected for the main tunnel. 08
The project framework reaches Parliament
Committee papers recommended a NOK 26.3 billion ceiling in 2014 prices. 07
First ceremonial blast at Åsland
The transport minister marked the start of preparatory excavation. 11
Assembly caverns and logistics tunnels
AF Gruppen’s contract with AGJV supported the main tunnel construction. 12
The first TBM begins
The official launch began the northward boring programme. 13
Condotte seeks protection
The company petitioned for bankruptcy protection in Rome. 19
Northern breakthroughs
Two machines reached the caverns beneath Ekeberg. 13
Skanska wins on appeal
Borgarting awarded NOK 272.8 million in procurement damages. 21
Opening moved to December 2022
Bane NOR announced a further year and requested a higher cost ceiling. 02
Main tunnel boring completed
The final two machines broke through near Ski. 14
The Skanska payment
The recorded payment including interest was NOK 345 million. 22
A revised commitment ceiling
Parliament authorised NOK 30.907 billion for the project. 24
The 2021 budget framework
Parliament authorised a NOK 36.570 billion project ceiling. 25
Energisation begins
The contractor began energising the tunnel’s electrical distribution system. 16
Passenger service opens
The new direct railway began carrying ordinary passenger trains. 28
Royal opening ceremony
The ceremonial opening followed the start of traffic. 28
Fire stops the railway
Heat and fire in the power-cable system closed the line. 28
Another fire during tests
The electrical system failed again while repairs were being tested. 28
Further heating at Ski
Heating and smoke affected the switching building serving traffic south of Ski. 31
Test running resumes
The railway entered a further period of test running. 32
Passenger trains return
Normal passenger service resumed after the long closure. 29
A conductor breaks
Alkaline dripping damaged a conductor and a train stopped in the tunnel. 33
Both bores checked
The tunnel was closed for checks after the May failure. 33
Independent reviews report
The government-commissioned review examined the failed opening and project decisions. 28
Ice beside the contact system
Bane NOR recorded ice formation affecting the tunnel’s electrical equipment. 35
The rebuilding campaign starts
Work proceeded one bore at a time, with other trains using Østfoldbanen. 39
The state auditor follows up
Riksrevisjonen criticised incomplete implementation of improvement measures. 03
Reliability after rebuilding
Jernbanedirektoratet reported high reliability and 91.7 percent punctuality. 41
Criminal judgments
TI Norge’s court compilation records two final convictions linked to private work charged to the project. 43
Åsland restoration permit
The permit set runoff limits and continued monitoring requirements. 47
AGJV judgment
The district court issued its judgment in the tunnel-contract dispute. 44
The appeal is reported
Bane NOR confirmed that AGJV had appealed the judgment. 45
Closing works in the budget proposal
The 2027 proposal retained the ceiling and forecast further closing expenditure. 48