Porsgrunn–Skien–Nordagutu
The industrial railway through Telemark
A railway begins with water
Hydro's factories had to stand near the waterfalls that supplied their electricity. That placed production inland, far from the seagoing ships carrying fertiliser to world markets. From 1909 the route out of Rjukan combined railway, a train ferry across Tinnsjøen, another railway to Notodden and barges down the waterway towards Skien. Every transfer needed labour, quays and dependable connections. Bratsbergbanen emerged from the cost and vulnerability of that final waterborne stage. 04
A larger canal or a new railway?
A railway was not the only answer considered. In 1910 engineer Sigurd Kloumann promoted an enlarged canal connection towards Norsjø. The proposal also raised a question about who would control the export trade: a stronger port at Notodden threatened established interests farther downstream. Kloumann's departure from Hydro in 1911 weakened the canal campaign, while Sam Eyde preferred investment in a railway. Prime Minister Gunnar Knudsen helped the railway proposal forward in 1913. The choice redirected industrial investment, but did not instantly empty the waterways; barges continued working after the new line opened. 05
Where a national route met Hydro's plans
Parliament had authorised the Notodden–Hjuksebø connection in 1908. The 1913 decision extended the project towards Skien and a meeting with the existing Vestfold railway at Eikonrød. The government and Hydro agreed on a railway company with public and industrial interests, with the line intended to serve the next expansion of Rjukan's factories. It was simultaneously a national railway connection and a transport investment for a particular manufacturer. 03
Knudsen saw the advantage of connecting the developing Sørlandsbanen to Skien. Eyde supported the scheme on condition that Notodden was connected to Hjuksebø. The junctions were part of the bargain from the beginning. 28
A new corridor through Telemark
The undertaking involved more than laying track between the factories and the coast. New stations, bridges and cuttings had to carry a main railway through inland Telemark. On the Notodden approach, Hjukse bridge rose 65 metres above the valley below, one of the conspicuous engineering works of the historic route. That bridge now belongs to the Tinnosbanen section of the Notodden journey. 06 02
The station buildings gave the new railway a recognisable character. Gudmund Hoel's NSB architectural office designed the 1916–18 generation with neo-Baroque details, including the richly treated Nordagutu building. These were permanent public places as well as industrial infrastructure. 03
Freight first, passengers afterwards
Hydro began using the new route for freight in 1916. General passenger traffic between Notodden and Eikonrød followed on 17 December 1917. The different dates explain why Bratsbergbanen has more than one opening anniversary: an industrial railway could already be earning its keep before the public ceremony. King Haakon took part in the formal opening on 10 February 1920. 06
Skien gains a station and loses convenience
The new through route changed Skien's relationship with its railway. The station was placed north of the old centre, giving the new line a workable alignment but leaving passengers farther from the streets they wanted to reach. The former central station lost its previous role, and local pressure later brought trains back there for a time. Railway access became a prominent issue in plans for the growing city. Bratsbergbanen's industrial advantages therefore came with an everyday urban argument: a route useful to through traffic did not automatically provide the most convenient arrival for Skien's residents. 07
Porsgrunn, Eidanger and the break of gauge
The railway through Porsgrunn already existed as part of the narrow-gauge Vestfold route. The arrival of standard-gauge trains from inland Telemark changed the southern network's organisation. Skien–Brevik became associated with Bratsbergbanen, while passengers and goods meeting the narrow-gauge Vestfold line encountered a break of gauge at Eidanger. Railway enthusiast Finn S. Holom remembered 1950s Porsgrunn unmistakably as a Bratsberg station: a busy goods shed, loaded delivery lorries and tracks handling far more than passenger arrivals. The names used for today's services can conceal that earlier geography of work and interchange. 08
Daily supplies for Herøya
When the new Herøya factories were ready in 1929, they depended on daily deliveries of liquid ammonia from Rjukan and Notodden. Tank wagons carried a raw material essential to fertiliser production, but the final approach to Herøya still involved barges from Borgestad. The planned connection through Porsgrunn took many more years to complete. Bratsbergbanen was therefore part of a changing transport system, in which modern electric railways and waterborne transfers continued side by side. Its value lay in keeping the factories supplied as much as in taking finished goods away. 09
The industrial route enters the labour conflict
The Menstad confrontation of 8 June 1931 belonged to the same industrial landscape. During a prolonged lockout, Hydro wanted to move stored goods and maintain its commercial connections. Contract workers at Menstad continued loading and unloading; the union regarded their work as strikebreaking. Demonstrators confronted police, and military forces were brought into the conflict. The dispute was about control over industrial work and the movement of goods, rather than a strike by Bratsberg's railway staff. It exposed the tension beneath a transport system often described only through engineering achievements and export figures. 10
Electric traction arrives in stages
The older Tinnosbanen had electric trains from 1911. Bratsbergbanen's electrification came later, with 1936 and 1949 marking the principal stages in the Directorate's railway history. It is therefore misleading to give the entire modern corridor one early electrical opening date. 01 04
During the occupation, the electric route reached Borgestad, while steam locomotives still worked Skien–Brevik and the narrow-gauge connection towards Larvik. The difference mattered when coal became scarce: the railway network was a mixture of traction systems whose limits shaped both passenger journeys and industrial deliveries. 12
A washed-out line and emergency barges
Heavy rain interrupted the industrial connection in April 1937. Near Nordagutu, between Skjei tunnel and Dalsvatn, a swollen stream washed away about 1,000 cubic metres of material over roughly 20 metres of railway. Track watchman Ottesen discovered the damage before the night train from Skien could reach it. Passengers and luggage were transferred to a train on the other side of the break. Hydro began arranging barge transport because Herøya's stocks would last only a couple of days. The episode showed how little room the production system allowed for a missing railway connection—and why the old waterway still mattered. 11
Travelling under occupation
The war changed ordinary journeys as well as freight priorities. Coal shortages brought service cuts in 1941, and travellers faced crowded trains and permits for longer journeys. Railway employees sometimes helped people travel without the papers demanded by the occupation authorities. They also assisted clandestine newspapers and refugees. The local account of wartime transport describes a railway serving restrictive official rules while some of its staff quietly worked around them. These actions were dangerous precisely because the railway was so visible: stations, luggage, timetables and inspections made a journey easy to monitor. 12
Herøya's factories in the German war economy
Occupation brought a darker industrial role. Hydro, IG Farben and Nordag became partners in Nordisk Lettmetall, with plans for aluminium and magnesium production at Herøya. The projects were tied to German demand for light metals. On 24 July 1943 Allied bombers attacked the industrial area; 55 people were killed. The light-metal scheme was abandoned, while fertiliser production restarted in November. These events affected the factories that Bratsbergbanen helped supply, even though the attack should not be mistaken for a bombing of the railway itself. 13
The wider transport chain also suffered the sinking of the railway ferry Hydro on Tinnsjøen on 20 February 1944. That event occurred on the Rjukan transport system, north of Bratsbergbanen, but interrupted the industrial connection of which the southern railway was a part. 09
An industrial network used by the resistance
The connections between Herøya, Notodden and Rjukan also carried information. Illegal newspapers circulated through Hydro's transport network, and employees formed resistance groups within the industrial community. The same relationships that kept production moving could help the underground movement reach people in several factory towns. 14
In November 1944 the resistance tried to prevent large transformers being sent from Herøya and Menstad to Germany. Participant Nils O. Nilsen described the special railway equipment and train ferry prepared for their removal. Two transformers at Herøya were destroyed; the attempt against the one already at Menstad failed. The episode connected railway handling, quays and the struggle over industrial equipment. 15
Svartufs bridge, 14 March 1945
Bratsbergbanen became a direct resistance target during Operation Betongblanding, the coordinated campaign against railway connections to ports around the Oslofjord. Its purpose was to obstruct the movement of German troops and equipment towards the fighting in continental Europe. Porsgrunn's harbour made the Bratsberg connection strategically important. 16
On 14 March 1945 an 18-man Milorg force attacked Svartufs bridge north of Nisterud. John Stensnes and Kjell Staal Eggen planned and led the action. The bridge stood over a ravine between two tunnels and was guarded by German soldiers. Fighting accompanied the demolition; the damaged bridge remained partly suspended, and traffic was stopped for more than two weeks despite intensive repairs. Local histories caution that the wider effect on German troop movements is difficult to measure. The immediate result is clearer: this railway connection could not be used while the bridge was out of service. 16
Forced labour in the district around Valebø
Soviet prisoners of war were requisitioned for forestry in Valebø and Kilebygda during the occupation. Their work supplied an economy directed towards German needs, in a district already shaped by the railway and Hydro's factories. The prisoners' experience belongs to the history of the communities along the line. 17
The 1950 collision at the shared junction
On 15 November 1950 the northbound Sørland express collided with runaway freight wagons between Hjuksebø and Holtsås. Passengers and railway staff lost their lives. Shunting at the junction had allowed wagons to reach the falling line towards the approaching express. The disaster belongs to the history of the connected Telemark railway network, although the accident site is on today's Sørlandsbanen rather than the present Porsgrunn–Nordagutu Bratsberg line. Hjuksebø's combination of through trains, branch traffic and goods handling is essential context for understanding why this junction mattered. 18
National ownership and a changing industrial purpose
The joint Tinnoset–Porsgrunn railway arrangement lasted into the post-war period before full state ownership in 1955. The system that had grown around Hydro became part of the wider national railway organisation. 04
Centralised traffic control followed on Bratsbergbanen in 1972. 01
A more fundamental change came in 1991, when the end of fertiliser production at Rjukan removed the traffic underpinning the northern railway and ferry chain. Trains continued between Notodden and the national network, but the original daily industrial journey from Rjukan to the coast had ended. The remaining passenger service now needed a purpose and funding arrangement beyond the factory transport for which the route had been built. 02
Who would pay for the passenger railway?
The passenger service's future became a repeated political question. Following the withdrawal of the service in 2000, Telemark county sought responsibility for buying a replacement service. By 2004 NSB was operating under a county contract. In 2011 the Ministry of Transport took over purchasing through a four-year trial. Parliamentary discussion concentrated on stability, marketing and attracting more passengers, while representatives worried that responsibility might return to the county. The issue was no longer whether Hydro needed an export railway. It was whether towns in Grenland and inland Telemark would retain a dependable public connection, and which level of government would sustain it. 19
The ground disappears beneath Notodden's tracks
During the night leading into 24 July 2011, intense rain caused Vålabekken to overflow at Notodden. Floodwater washed out the ground beneath the railway at the station. NVE identified this as the most severe local damage during the regional flood. The pictures of track hanging over a deep breach recorded a failure beneath the railway, rather than an ordinary inundation covering intact rails. 20
The southern station yard beside Heddalsvatnet became a crater of about 4,300 square metres. Rails, sleepers and overhead-line masts were left suspended. Around 15,000 cubic metres of earth had been lost after a culvert blocked and water flooded through the site. The destruction was concentrated in the yard; the protected 1917 station building survived. Notodden is now on Tinnosbanen, but the collapse severed the Notodden end of the Bratsberg passenger journey and damaged a central place in its industrial history. 22 21 23
Rebuilding an inherited railway
The work in 2012 had to restore a railway while preserving the character of its historic structures. Jernbaneverket replaced rails and points and dismantled overhead-line masts and cross-spans for repair. Matching the form of older equipment became part of the task, alongside rebuilding the washed-out ground. Hydro's contemporary account described 30 people working on the project and close cooperation with heritage interests. The damage had arrived just as formal protection of the Hjuksebø–Tinnoset railway was being completed. The repair consequently preserved evidence of the railway's industrial past as well as restoring its usefulness. 21 25
Notodden's two passenger destinations
The location of the passenger terminus remained tied to the choice of traction. Electric trains replaced diesel trains in August 2015, using the old Notodden station as their destination. That brought passengers back to the protected station building, while the more central public-transport terminal still lacked the necessary electrical connection. 24 23
In December 2020 trains returned to the terminal after its track 3 was electrified. Today's Notodden passengers use the terminal, while the 1917 station remains a substantial reminder of the older railway. 23
A working connection beyond its first purpose
Bratsbergbanen still links Grenland with Sørlandsbanen. Limestone and harbour freight continue to give the southern railway an industrial role, and the route also provides an alternative connection when disruption affects the wider network. The Directorate identifies ageing overhead equipment as a renewal need. 01
Maintaining the existing route remains a continuing task. Bane NOR's October 2026 programme included overnight track tamping between Borgestad and Porsgrunn. Behind the modern passenger timetable is the same underlying obligation as in the industrial years: a railway connection remains useful only while its track and structures are kept in service. 26
Continue exploring: Vestfoldbanen — the shared Grenland corridor · Sørlandsbanen — the inland junctions · Norway's railway story.
A railway in dates
The railway through time
The coastal railway reaches Skien
The Larvik–Skien section of the narrow-gauge Jarlsberg railway opens on 23 November, establishing the older railway through Porsgrunn. 27
A connection towards Hjuksebø is authorised
Parliament approves the Notodden–Hjuksebø railway that will help join Hydro's network to the developing national route. 03
The northern transport chain opens
Railways and train ferries connect Rjukan with Notodden; the onward journey towards the coast remains waterborne. 04
Canal and railway plans compete
Kloumann's canal proposal gives way to the railway scheme supported by Eyde and Knudsen. 05
The extension to Skien is approved
The project is planned to meet the existing railway at Eikonrød and serve Hydro's expanding factories. 03
Hydro freight begins
Industrial trains begin using the new connection before the general passenger opening. 06
Herøya needs daily ammonia
The new factories depend on supplies from Rjukan and Notodden, with barges still completing the final approach. 09
The Menstad confrontation
The lockout and continuing cargo work bring demonstrators into conflict with police at Hydro's loading site. 10
Electrification in stages
Electric traction is introduced across the Bratsberg corridor in successive stages. 01
The line washes out near Nordagutu
Rain damages the railway near Skjei tunnel; passengers transfer across the break and Hydro arranges emergency barges. 11
Fuel shortages restrict travel
Coal shortages reduce regional rail services during the occupation, while permits limit civilian journeys. 12
Herøya is bombed
An Allied attack kills 55 people and damages the industrial complex; the light-metal project is abandoned. 13
The railway ferry Hydro is sunk
The sabotage on Tinnsjøen strikes the northern industrial transport chain connected to Bratsbergbanen. 09
Transformers become resistance targets
Resistance groups attack equipment intended for removal from Herøya and Menstad to Germany. 15
Svartufs bridge is attacked
Milorg damages the Bratsberg bridge north of Nisterud, interrupting traffic for more than two weeks. 16
The Hjuksebø disaster
The Sørland express collides with runaway freight wagons on the line towards Holtsås. 18
Full state ownership
The joint industrial and state railway arrangement passes into full national ownership. 04
Centralised control
Remote traffic control is introduced on Bratsbergbanen. 01
The old Rjukan freight chain ends
The closure of fertiliser production removes the traffic supporting trains north of Notodden and the railway ferries. 02
A new purchasing arrangement
After the passenger service's withdrawal, county initiatives lead to an NSB contract with Telemark. 19
The state resumes purchasing
A four-year trial transfers responsibility for buying the passenger service to the Ministry of Transport. 19
Rebuilding the historic yard
Jernbaneverket restores the washed-out railway and repairs historic overhead-line structures. 21
Electric passenger trains return
Diesel trains are replaced and the older Notodden station becomes the passenger terminus. 24
Trains return to the central terminal
Electrification of track 3 allows passengers to use Notodden's public-transport terminal again. 23