Present-day railway · Lysaker-Asker

Askerbanen

A newer pair of tracks built beside — and mostly beneath — the older railway, separating faster trains from local traffic through the western corridor.

Airport Express Train leaving Bærumstunnelen at Sandvika · 2014 · Espen Franck-Nielsen · CC BY-SA 4.0
Built in stages2001-2011
Line standardUp to 160 km/h
Longest named tunnel5,790 m
Combined corridorFour tracks
ExploreRailway linesAskerbanen

Between Lysaker and Asker

Two railways
Four tracks

Askerbanen did not replace Drammenbanen. It gave the same corridor another pair of tracks.

Askerbanen runs from Lysaker via Sandvika to Asker. Beside it, the older Drammenbanen continues through the local stations. The two railways meet at the three larger stations but do different work between them. 01

The later project evaluation describes the practical division: freight, airport, long-distance and regional trains use Askerbanen, while local trains use Drammenbanen. Separating stopping patterns is what turns four rails into useful capacity. 05

LysakerSandvikaAsker
Faster servicesAskerbanen
Local stationsDrammenbanen

Lysaker-Asker · 1985 to today

The railway that made room

Askerbanen is a modern history of capacity: first recognising that the old railway could not carry every kind of train well, then spending almost two decades deciding how to give each kind of traffic space.

01

Two tracks had become one bottleneck

By the time the project took shape, Drammenbanen's capacity through the western corridor was fully used. Local trains with frequent stops shared the same pair of tracks as regional, airport, long-distance and freight services. A faster train could not simply pass a stopping train; the timetable had to make every movement fit the same railway. 01 05

The need for intervention appears in public planning as early as 1985-86 and again in Oslo Package 2 in 1997. The stated aims were broader than speed: more capacity, better punctuality, shorter journey times and a larger share of travel by public transport. 04 05

The problem was not simply too few rails
Fast and stopping trains were asking the same two tracks to do opposite jobs.
02

Eighteen years from idea to complete line

NSB presented the project in 1993 as a new double track from Skøyen to Asker. The first impact assessment considered a wide range of possible routes. A second assessment in 1996 recommended a surface station at Lysaker and a railway in tunnel westwards towards Engervannet — recognisably the solution eventually built. 05

Municipal plans through Bærum and Asker were adopted in 1998. The project did not then move straight into construction. Route choices, the order of the stages, the future of Fornebu and the detailed design were still being argued and tested. Vista Analyse counts roughly eighteen years from the planning start to completion of Lysaker-Sandvika. 05

1993Project launched
18 yrsPlanning to completion
3 stagesOne complete corridor
03

The new railway would go via Lysaker

Fornebu made the route decision more complicated. Oslo asked for alternatives that took the main railway by the redeveloping former airport. A 2001 supplementary study compared those options with the route through Lysaker. 05

The government chose the H alternative: the new double track would serve Lysaker rather than loop through Fornebu. The assessment judged it better suited to the railway's transport task, less expensive, easier to build in stages and faster for regional passengers. A separate public-transport connection was intended to link Fornebu with Lysaker. 05

04

It was built from the outside in

The 1996 planning work originally placed other sections ahead of Sandvika-Asker. A later national analysis reversed that order after finding the strongest early socio-economic benefits in the outer sections. Sandvika-Asker therefore became the first construction stage, built from 2001 and opened in 2005. 02 03 05

This gave the corridor a new pair of tracks only west of Sandvika. It was strategically useful, but incomplete: trains still had to share the old bottleneck farther east. The later evaluation is important here because it does not pretend that laying the first rails immediately delivered the whole promised result. 05

05

A railway mostly hidden from view

The fast pair spends much of its journey in rock. Its four principal named tunnels are Bærumstunnelen, 5,790 metres; Tanumtunnelen, 2,790 metres; Skaugumtunnelen, 3,790 metres; and Askertunnelen, 416 metres at the Asker station area. 05

01 · Lysaker-Sandvika5,790 mBærumstunnelen
02 · Sandvika-Asker2,790 mTanumtunnelen
03 · Sandvika-Asker3,790 mSkaugumtunnelen
04 · Asker station416 mAskertunnelen

Around Sandvika, four concrete tunnels carry their own names and lengths: K73 at 243 metres, K72 at 197 metres, K74 at 108 metres and K91 at 397 metres.

The tunnel alignment kept most of the new railway away from dense residential areas. The 2021 evaluation found that this reduced conflict with vulnerable nature and cultural environments and improved long-term noise exposure compared with a surface solution. 05

06

Lysaker had to become part of the new railway

The station was more than a platform project. It grew from two to four platform tracks, gained a broad passage beneath the railway and was connected more closely with buses and taxis. The project also included 0.9 kilometres of new double track and a new railway bridge over Lysakerelva. 04 05

Construction work began in the mid-2000s, and the rebuilt station officially opened on 1 September 2009. That removed one bottleneck and prepared the eastern end for the final connection to Sandvika. 02 05

07

The last gap went under Bærum

The first of four major Lysaker-Sandvika contracts began in March 2007. The new alignment runs beneath the villa districts from Lysaker towards Engervannet, then reaches daylight and approaches Sandvika alongside the older railway. The project built 5.6 kilometres of new double track in this final section, including the 5,790-metre Bærumstunnelen. 05

The complete facility entered service on 26 August 2011 and received its official opening on 2 September. With that, four tracks extended continuously from Lysaker to Asker. 04 05

Bærumstunnelen excavation site at Skallum in April 2009
Bærumstunnelen excavation at Skallum · 24 April 2009Punkmorten / Wikimedia Commons · Public domain
08

Four tracks work because the trains are separated

Askerbanen was built to a standard allowing 160 km/h. The older Drammenbanen remains a railway of local stations and lower speeds. In practice, the new pair carries freight, airport, long-distance and regional traffic while the older pair carries the local trains. 01 05

The project target was capacity for 26 trains in each direction per hour after the complete programme. A local stop at Høvik or Blommenholm no longer has to occupy the same path as a through train beneath Bærum. 05

09

New tracks were necessary, but not sufficient

The 2012 evaluation of the first Sandvika-Asker stage was restrained. Only marginal timetable improvements had been made, so the expected socio-economic benefit had not yet appeared — even though the investment was still judged strategically right. New rails create possibilities; they do not write a better timetable by themselves. 05

Later service changes, new rolling stock, more stabling capacity, power-supply work and renewal of the older Drammenbanen allowed more of the corridor's capacity to be used. In 2021, Vista Analyse's evaluation of Lysaker station and Lysaker-Sandvika found high goal achievement and socio-economic value substantially better than forecast. The Railway Directorate's summary says the works helped shift the competitive balance between car and train more than expected. 04 05

Askerbanen's value emerged as train services and the surrounding railway were adapted to use the new capacity.

The whole project in time

From first plans to a four-track corridor

The need is recorded

Government work on the western corridor describes congestion and the need for more transport capacity.

A new double track

NSB launches the Skøyen-Asker double-track project through an environmental impact assessment.

The built idea appears

The second assessment recommends Lysaker at the surface and a tunnel from west of Lysaker towards Engervannet.

A route through two municipalities

The impact assessment is approved and municipal plans for the new double track are adopted in Bærum and Asker.

The order changes

The national transport plan moves Sandvika-Asker to the front because the outer section offers the strongest early benefits.

Via Lysaker, not Fornebu

The government selects the H alternative through Lysaker and work begins on the Sandvika-Asker stage.

The western stage opens

Sandvika-Asker enters service; the Lysaker station project also begins.

Lysaker becomes a worksite

The first construction work starts around Vollsveien as the bottleneck station is rebuilt.

The final double track begins

The first of four major contracts for Lysaker-Sandvika starts in March.

New Lysaker station

The four-platform-track station officially opens on 1 September.

Four tracks to Asker

The complete Lysaker-Sandvika facility enters service on 26 August and is officially opened on 2 September.

A cautious first verdict

An evaluation of Sandvika-Asker finds that the new tracks had not yet produced the expected timetable benefits.

The timetable catches up

Service changes, new rolling stock and supporting works begin to use more of the capacity the railway created.

The full result is measured

Vista Analyse concludes that the two final projects were successful and more socio-economically valuable than forecast.

Sources

The faster railway beneath Bærum

Open each original source, or use Google Translate to read Norwegian pages in English.

06
Espen Franck-Nielsen / Wikimedia Commons

Airport Express Train leaving Bærumstunnelen at Sandvika, 2014

Open source
07
Punkmorten / Wikimedia Commons

Bærumstunnelen excavation site at Skallum, 2009

Open source

The complete chain

Oslo-Bergen
Line by line

Every railway beneath the journey now has its own history — including the older Vossebanen layer beneath the western end.

See the complete railway chain